Hebei Sitong New Metal Materials Co., Ltd
Self provided emergencyLNGPublicity of environmental protection acceptance upon completion of gasification station project
In accordance with the Regulations on the Administration of Environmental Protection of Construction Projects (Decree No. 682 of the State Council), the Interim Measures for Environmental Protection Acceptance of Completed Construction Projects (GHGHA [2017] No. 4), and the Guidelines for the Examination and Approval of Environmental Impact Assessment Documents of Construction Projects and the Acceptance of Self developed Environmental Protection Facilities by the Owner (for Trial Implementation) (JHBH [2017] No. 727), Pollution Impact Category of Technical Guidelines for Environmental Protection Acceptance of Completed Construction Projects (Announcement No. 9, 2018 of the Ministry of Ecological Environment), the environmental protection acceptance of the completed emergency LNG gasification station project of Hebei Sitong New Metal Materials Co., Ltd. is hereby announced as follows:
(1)Project name: Hebei Sitong New Metal Materials Co., LtdSelf provided emergency LNG gasification station project
(2) Construction unit: Hebei Sitong New Metal Materials Co., Ltd
(3) Construction site: No. 359, Fazhan West Street, Economic Development Zone, Qingyuan District, Baoding City
(4) Publicity content: acceptance report, inspection report, acceptance comments and other information, see the appendix for details
(5) Publicity time: September 22, 2020 to October 22, 2020
During the publicity period, if you have any objection to the above publicity content, please give feedback in written form. Individuals must sign their real names and units must affix their official seals.
Contact: Liu Xiaoquan
Tel.: 13833059068
Appendix 3: Acceptance Opinions